Pharmacy ERP · delivery · team view

Sprint 1 — Catalog & billing slice

→ · day 28 of 28 · gate due

Gate

Printer prints on real hardware · search under 2s at 50k rows · contract published · cross-tenant read fails

2 Blocked needs a decision
2 Ready to start
0 In flight
0% Sprint complete 0 of 62 hours

Blocked — founder decision required

These stall other people's work. Clearing them is the highest-value use of founder hours this week.

PH-021 Blocked

Decide the drug master data source

4h · product ·Tier 3 · founder approval ·P0

Founder decision required. Was a Month 1 (May 2026) decision and is still open. Hard-blocks catalog, search, GST slab, HSN, and Schedule H1 flagging.

Unblocks PH-030 PH-031

PH-022 Blocked

Decide cloud provider, India region, and stand up staging

8h · infra ·Tier 3 · founder approval ·P0

Founder decision required. Blocks SMS provider integration, object storage for OCR, and any deployed environment.

Tier 3 — hard stops awaiting founder approval

Compliance stops under CLAUDE.md. These cannot merge without written approval, and Claude does not decide them.

Sprint board

Backend developer 24h

PH-006 Draft

Sprint 0 backend carry-over — auth rate limit, contract assertions, audit integrity, harness gaps

14h · backend ·Tier 3 · founder approval ·P0
PH-025 Draft

Idempotency-Key interceptor for all mutating endpoints

10h · backend ·P1

Unblocks PH-040

Flutter developer 18h

PH-016 Ready

Reconcile the app's local schema with the ratified server schema (ADR-0004)

8h · flutter ·P0

Startable now

Unblocks PH-030

PH-017 Draft

Sprint 0 Flutter carry-over — token colour-diff guard and toolchain re-measurement

10h · flutter ·P0

Road to the pilot gate

Re-baselined 2026-07-25. Paid-pilot go/no-go on 31 Jan 2027 — see ADR-0003.

  1. S0 Foundations & de-risking 07-27 – 08-09
  2. S1 Catalog & billing slice 08-10 – 09-06
  3. S2 Offline, sync & ledger 09-07 – 10-04
  4. S3 Purchase, OCR & first alpha 10-05 – 11-01
  5. S4 Compliance, reports, khata 11-02 – 11-29
  6. S5 Hardening & pilot readiness 11-30 – 12-27
  7. S6 Paid / freemium pilot 12-28 – 01-31